Medicare Part C and Part D Reporting Requirements Data Validation Readiness

Medicare Part C and Part D data validation is an annual independent review of specified Reporting Requirements data. Sponsors reporting Part C or Part D data participate unless a CMS exemption applies; the current manual sets April 1 to June 15 of the following year as the review period. Integral Healthcare Solutions (IHS) provides readiness consulting by drafting reporting documentation and running a documentation pre-assessment for sponsor staff approval; it does not perform independent validation.

Last updated: November 2026

What is the Part C and Part D annual data validation program?

It is a yearly independent audit of the data a sponsor reports to CMS under the Part C and Part D Reporting Requirements. 42 CFR 422.516(g) (Part C) and 42 CFR 423.514(j) (Part D) each require a yearly independent audit of the reported information under CMS's specifications. CMS calls the audit retrospective: CY 2022 data, for example, was validated in 2023. Sponsors must acquire external resources (CMS data validation page, last modified August 6, 2026; all sources opened November 25, 2026).

The CMS Data Validation Procedure Manual, December 2025, sets the mechanics (page opened November 25, 2026). The review runs April 1 to June 15 and covers HPMS data submitted by the applicable deadline or March 31 resubmission cutoff. If March 31 is a weekend or federal holiday, resubmissions are due before 11:59 p.m. on the preceding business day. Contractors cannot validate data absent from HPMS or submitted or resubmitted after March 31. The 2026 manual puts seven sections in scope: Part C grievances, organization determinations and reconsiderations, and special needs plans care management; Part D medication therapy management, grievances, coverage determinations and redeterminations (including at-risk redeterminations under a drug management program) and reopenings, and improving drug utilization controls. It excludes others, including enrollment and disenrollment, "at this time."

What is at stake if a contract scores below 95 percent?

CMS set 95 percent as the passing threshold for every reporting section. CMS reduces to one star the Star Ratings measures based on that data when a contract does not score at least 95 percent on the applicable reporting section or is not compliant with the standards for data used directly in the measure (42 CFR 422.164(g)(1)(ii) and 423.184(g)(1)(i)). For sections subject to validation, the CY 2022 public-use-file specifications exclude contracts that did not pass (page opened November 25, 2026).

What changed for the next reporting year?

CMS lists draft CY 2027 technical specifications dated October 2026 with a stated effective date of January 1, 2027 (draft; CMS reporting requirements page, last modified October 28, 2026). The draft combines the Part C and Part D specifications into one document, says HPMS has combined Part C and Part D grievance reporting as of CY 2027, and clarifies several sections, including special needs plans care management timing and medication therapy management.

Who needs it and what triggers it?

Every sponsor that reports Part C or Part D data, regardless of enrollment size, unless a manual exemption applies. Delegating collection, calculation or reporting for any section or data element requires the contractor to review the delegated entity's data and reporting processes for each applicable contract. Draft specifications, system changes, delegation and low scores can prompt readiness work; they do not independently trigger the annual validation obligation.

StepWhoTiming in the manual
Select the independent contractorSponsorDecember to March, beginning the year before the review
Notify CMS and request HPMS accessContractor and sponsorJanuary to April
Complete the Organizational Assessment Instrument (OAI); send it and supporting code/procedures no earlier than April 1SponsorMarch to April
Site visit, on-site or virtualContractor and sponsorEarly April
Findings submitted to CMSContractorBy June 15
Appeal, if the sponsor disagreesSponsor5 business days after the deadline

Source: Manual December 2025, Exhibit 2 and §§4.1, 6.2.3; page opened November 25, 2026.

How does IHS help?

IHS does not act as the sponsor's data validation contractor. CMS Appendix A says companies that provide management consulting or assist with reporting procedures, processes or information systems may not serve as the contractor for that sponsor, and lists a firm hired for a pre-assessment before or during April 1 to June 15 as not independent. Its footnote prohibits validating reporting-period data for which the contractor supplied management consultation or assistance. It also says a sponsor may hire a separate firm for mock audits before the formal review period if that firm differs from the one performing the review (Appendix A, June 2025). IHS provides that separate readiness support and does not select or supervise the contractor.

IHS drafts, for the sponsor's staff to correct and approve:

The sponsor supplies report owners, process documentation, code, extracts and copies of relevant HPMS records; its authorized users retain system access. The real limit: IHS reviews documentation and process. It does not write production code, run extracts or certify that code produces correct counts; that belongs to the sponsor's analysts and the independent contractor. IHS does not log in to HPMS, contact CMS or file anything.

What should you have ready?

Linked sources were opened November 25, 2026.

  1. A per-contract list of in-scope sections and deadlines, including the March 31 cutoff and its preceding-business-day exception (CMS DV Manual, December 2025, §1.2 and Exhibit 3)
  2. Secured, retrievable source documents and outputs, documenting all required fields with meaningful, consistent labels and the correct reporting periods and levels (Standard 1) (CMS DV Manual, December 2025, Exhibit 5)
  3. The code, queries or formulas in the version used for the reporting period, error-free and version-controlled (Standard 1) (CMS DV Manual, December 2025, Exhibit 5)
  4. Written population logic, exclusions and quality-check thresholds (Standard 2) (CMS DV Manual, December 2025, §3.4.2.2.2)
  5. Implemented procedures checking final-data completeness and accuracy, source-document agreement, counts, ranges, calculations, missing data, version control, and logical errors and outliers (Standard 3) (CMS DV Manual, December 2025, §3.4.2.2.3)
  6. The archive of source, intermediate and final data sets, other outputs used for CMS entry, and support for HPMS submissions and resubmissions (Standard 4; CY 2026 Part C Reporting Requirements) (CMS DV Manual, December 2025, Exhibit 12)
  7. Evidence of implemented procedures for periodic system updates and restoration of data in each system (Standard 5) (CMS DV Manual, December 2025, Exhibit 12)
  8. If systems changed during the reporting period, evidence of correct implementation and no adverse data impact; if collection or reporting is delegated, evidence of routine monitoring of data quality and timeliness (Standards 6 and 7) (CMS DV Manual, December 2025, Exhibit 12)
  9. The selection record, current-year contractor training certificates, retention plan and CEO-signed access letter covering users, access functions, training and contract numbers (CMS DV Manual, December 2025, §§3.2.1 through 3.2.2 and 6.1)
  10. A calendar that works back from April 1: CMS estimates the OAI takes at least two weeks, and contractor staff credentials for the HPMS module take about four weeks (CMS DV Manual, December 2025, §§3.2.2.3.4 and 4.1)
  11. An appeal file of evidence that existed when the review ran (CMS DV Manual, December 2025, §6.2.3)

Bring this list to a free introductory call.

How does this compare with other approaches?

OptionWho does itWhat CMS says
Independent contractorAn external firm meeting Appendix ARequired each year; reports findings to CMS; may not perform mock audits or pre-assessments for the same data.
Separate pre-assessment firmA firm other than the contractorAllowed before the formal review period; cannot then be that sponsor's contractor.

This validation is separate from IHS's CMS program audit readiness, Medicare Advantage and Part D compliance program and Star Ratings improvement services.

What does it cost?

CMS does not publish a fee for data validation or its contractors on the pages reviewed; fees depend on scope under the sponsor's own contract. The manual information-collection statement estimates an average of 30 hours per response, not consulting fees (page opened November 25, 2026). IHS scopes each engagement after a free introductory call.

What this is not

Frequently asked questions

Who has to complete the annual Part C and Part D data validation?

Sponsors reporting Part C or Part D data participate regardless of enrollment size, subject to the manual's exemptions: PACE, Part C Health Care Prepayment Plans, organizations/sponsors non-renewing or terminating a contract during the measurement year, and contracts terminating before July 1 of the following year. Terminating a plan does not exempt an otherwise applicable contract remaining active through that July 1. Employer Group Waiver Plans and all-800-series plans have an enrollment/disenrollment-section waiver; mixed contracts may exclude their 800-series plans from that section.

When does the data validation review happen?

The current manual sets April 1 to June 15 of the following year, with findings due June 15 and contractor selection before April 1. March 31 is the resubmission cutoff; if it falls on a weekend or federal holiday, resubmissions are due before 11:59 p.m. on the preceding business day. Contractors cannot validate data absent from HPMS or submitted or resubmitted after March 31.

Which reporting sections are validated?

The CY 2026 manual lists seven sections, named above. CMS can change the list.

What score passes, and what happens to a contract that falls short?

CMS set 95 percent as the passing threshold for each reporting section. A contract that misses 95 percent on a section, or the standards for data used directly in a measure, has the related Star Ratings measures reduced to one star under 42 CFR 422.164(g) and 423.184(g). For sections subject to validation, the CY 2022 public-use-file specifications exclude contracts that did not pass.

Can the firm that helps with reporting also be the data validation contractor?

No. CMS's Appendix A says companies that provide management consulting or assist the sponsor with reporting procedures, processes or information systems may not serve as the contractor for that sponsor. Integral Healthcare Solutions does not act as the sponsor's data validation contractor.

Can a sponsor fix its data once the review has started?

Corrections submitted after March 31 cannot be validated; the preceding-business-day exception described above also applies to resubmissions. Appeals are due five business days after the validation deadline and must rely on documentation that existed during validation.

How long must a sponsor keep the records?

The manual specifies ten-year retention for the validation archive and contractor-selection records. Federal inspection and audit rights extend ten years after the final contract period or audit completion, whichever is later, with extensions for specified circumstances. CMS may require longer retention upon determining a special need and giving at least 30 days' notice before normal disposition; termination, dispute or alleged fraud or similar fault can extend retention to six years after final resolution, and CMS's determination of a reasonable possibility of fraud or similar fault permits inspection at any time.

Source: 42 CFR 422.504(d) and (e) and 423.505(d) and (e), page opened November 25, 2026.

Does Integral Healthcare Solutions submit anything to CMS?

No. Integral Healthcare Solutions drafts documentation, the pre-assessment gap list and draft answers for the sponsor's staff to approve. The sponsor handles its submissions and correspondence, and its independent data validation contractor submits the validation findings to CMS.

Talk with IHS's CEO

A 30-minute introductory meeting with Thomas G. Goddard, JD, PhD, to scope what your organization needs.

Schedule a Free Discovery Session